Engineering and infrastructure serving strategic projects.

High-Voltage/Low-Voltage Substations: Key Steps to a Successful Installation in Morocco

High-Voltage/Low-Voltage Substations: Key Steps to a Successful Installation in Morocco

MV/LV Electrical March 2026 6 min read

An HTA/LV (Medium Voltage/Low Voltage) transformation substation is the heart of any industrial or commercial electrical infrastructure in Morocco. It converts the ONEE high voltage supply (15,000 V or 20,000 V) into usable low voltage (400 V / 230 V). If poorly sized or improperly installed, it poses a major risk to business continuity and personal safety. In this article, the INGTELMA team walks you through the key steps of a successful installation.

1. Preliminary Study: Sizing Before Installing

Before purchasing any equipment, a thorough technical study is essential. This phase determines the required transformer capacity (expressed in kVA), the type of substation suited to the site, and the regulatory constraints to be met.

  • Power assessment: inventory of all electrical loads on-site (machinery, lighting, air conditioning, UPS systems, etc.) with their simultaneity and diversity factors.
  • Transformer capacity selection: typically 160, 250, 400, 630, or 1000 kVA based on calculated demand, with a 20–30% reserve for future expansion.
  • Substation type: masonry cabin substation, prefabricated concrete substation, or pole-mounted substation depending on available space and ONEE requirements.
  • Short-circuit study: calculation of short-circuit current to size the protection devices (MV circuit breakers, LV fuses).
INGTELMA Tip: Never undersize your transformer. An overloaded transformer ages prematurely and fails at the worst possible time. Always plan for headroom.

2. Administrative Procedures and ONEE Approval

In Morocco, any connection to the ONEE MV network is subject to a strict regulatory process. Only companies certified by ANRE (National Electricity Regulation Authority) are authorized to carry out this work.

  • Mandatory MV-LV certification: the contractor must hold an MV-LV certification issued by ANRE. INGTELMA holds a Class 3 certification with no power limit.
  • ONEE technical file: single-line diagram, site layout plan, calculation report, transformer data sheet — to be submitted for approval before work begins.
  • Connection agreement: signing of an agreement with ONEE defining the connection conditions and responsibilities of each party.
  • Road permit: required if the work involves trenching in public land for the MV supply cable.

3. Civil Works: The Foundation of Safety

The civil engineering aspect of a transformation substation is often underestimated. Yet poor execution can compromise the entire installation.

  • Excavation and foundation: digging and pouring a reinforced concrete raft slab designed to support the transformer weight (from 800 kg to over 3 tonnes depending on capacity).
  • Building construction: cinder block or reinforced concrete walls, anti-intrusion metal door, mandatory high and low ventilation for heat dissipation.
  • Grounding network: installation of separate MV and LV earth electrodes, in accordance with NFC 13-100 standard. Ground resistance must be below 1 ohm for MV substations.
  • Switching platforms: insulating floor covering in front of MV and LV panels to protect operators during switching operations.
  • Oil containment pit: mandatory for oil-immersed transformers, to contain any dielectric fluid leaks.

4. Substation Equipment: Materials and Installation

The equipment of an HTA/LV substation includes several critical components that must be carefully selected and installed according to best practices.

MV Side (Medium Voltage)

  • MV switchgear (RMU or modular cells): cable intake, transformer protection (fuses or circuit breaker), ONEE metering. Reference brands: Schneider Electric, ABB, Siemens.
  • MV supply cable: 15 kV or 20 kV cable with XLPE insulation, laid in trench or duct — length depends on the distance to the ONEE network.
  • HTA/LV transformer: oil-immersed or dry-type (resin) transformer, rated capacity as determined in the study. Minimum ingress protection IP 23.

LV Side (Low Voltage)

  • MSB (Main Switchboard): main circuit breaker, copper busbars, outgoing feeders to distribution boards. Rating based on the transformer's nominal current.
  • ONEE metering: metering cabinet with active and reactive energy meters, supplied and sealed by ONEE after inspection.
  • Reactive power compensator: capacitor bank to correct the power factor (cosφ) and avoid penalties on the ONEE electricity bill.
Safety: Any work on the MV switchgear must be carried out by personnel with at least H2V qualification, with prior isolation (lockout/tagout) and wearing high-voltage PPE (15 kV insulating gloves, face shield, insulating mat).

5. Commissioning and Testing

Commissioning a transformation substation is a critical step that cannot be improvised. It must be carried out in the presence of an ONEE representative and a qualified engineer.

  • Connection verification: checking the tightness of all terminals, measuring insulation resistance of MV and LV cables (5000 V megohmmeter).
  • Earth electrode testing: measuring ground resistance with an earth tester — must comply with values calculated in the study.
  • Protection checks: verifying protection relay settings, testing MV cell trip functions.
  • Progressive energization: MV energization by the ONEE agent, verification of LV voltage levels under load, no-load current measurement.
  • Acceptance report: document signed by ONEE, the client, and the contractor — mandatory for final connection.

6. Preventive Maintenance: Protecting Your Investment

A well-maintained transformation substation can operate without incident for 30 to 40 years. Without maintenance, failures typically occur within 8 to 12 years.

  • Annual inspection: cleaning switchgear cells, checking connections (infrared thermography), verifying transformer oil level, testing protection relays.
  • Oil analysis (every 3 years): dielectric and chromatographic analysis of transformer oil to detect internal degradation before failure occurs.
  • General overhaul (every 5 years): seal replacement, general retorquing of connections, verification and recalibration of protection devices.
  • On-call service contract: emergency response within 4 hours in case of failure, available 24/7.

Summary: Transformer Capacities and Their Applications

Capacity (kVA) Typical Application LV Current (A) Room Size (m²)
160 kVA Small industry, residential building ~231 A ~15 m²
250 kVA SME, medium-sized shopping center ~361 A ~20 m²
400 kVA Light industry, 4–5 star hotel ~577 A ~25 m²
630 kVA Heavy industry, free trade zone ~909 A ~30 m²
1000 kVA Large industry, data center ~1443 A ~40 m²

Conclusion

Installing an HTA/LV transformation substation is a demanding technical project that requires specialized expertise, regulatory certifications, and uncompromising execution rigor. Every step — from the study to the acceptance report — determines the reliability and lifespan of your electrical infrastructure.

Since 2009, INGTELMA has been delivering turnkey transformation substations for industrial, public, and commercial clients across Morocco. Our Class 3 MV-LV certification with no power limit and our H2V-qualified teams guarantee installations that comply with ONEE and NFC 13-100 standards.